Agreement with the City Council
In 2025, we signed a protocol with the City Council to find a new arrangement of port spaces in the city and achieve a phasing plan for the environmentalization of cruise traffic.
We move emissions away from the city
On October 2, 2023, we said goodbye to the last cruise ship operating at the Barcelona Nord dock and all cruise activity was transferred to the Adossat dock. By the end of 2026, operations at the Barcelona South Wharf are expected to come to an end.
What is included in the Port's agreement with the Barcelona City Council?
Restructuring of the cruise terminals
Limitation of the number of terminals
Relocation of cruise activity
Chronology of the process of moving away from the city's cruise terminals
- 2026
During the fourth quarter, Terminal S will be closed and Terminal C will be demolished.
Construction of Terminal G will be completed.
- 2027
Terminal G will become operational. Construction of the new Terminal C will begin.
- 2028
The berthing area of the former Terminals A and B will be rehabilitated.
Construction work will begin on a bridge identical to the Porta d'Europa Bridge.
- 2029
The berthing area of the former Terminals A and B will be rehabilitated.
Construction work will begin on a bridge identical to the Porta d'Europa Bridge.
- 2030
The twin Porta d’Europa Bridge will become operational.
The new Terminal C will become operational with three berthing positions.